As early as 2024
Anticipated groundbreaking
2019
Final Design
November 2018
Protea Waterfront Development presents first evolution of Seaport San Diego design concept.
March 2018
Protea Waterfront Development presents first evolution of Seaport San Diego design concept.
October 2017
Port enters into an Exclusive Negotiation Agreement with Protea Waterfront Development, LLC.
May 2017
Board directs staff to negotiate and enter into an Exclusive Negotiating Agreement for a period of two years with Protea Waterfront Development, LLC, the proposed managing member of 1HWY1, with a project description to be completed in one year.
November 2016
Board votes to select 1HWY1's proposal, while reserving certain rights on behalf of the agency.
June 2016
Port hosts an Open House, inviting the community to preview the six proposals and provide comments. More than 1,200 people attend.
May 2016
Due date for proposals. Eleven are received, and six proposals meet the criteria for consideration.
February 2016
Port issues Request for Proposals.
December 2015
Board unanimously votes to direct staff to seek development proposals for this area.
November 2015
Framework Report is accepted by the Board in November 2015, concluding the visioning phase.
October 2015
Board of Port Commissioners directs staff to move forward on a development strategy for the Central Embarcadero.
2014
Vision Statement and Guiding Principles are accepted by the Board of Port Commissioners.
2013
Port begins process with extensive public outreach, including 100 interviews with stakeholders and agencies.